Commercial project
Warehouse adapted around a live business, Dartford
A business in Dartford needed its warehouse reworked to suit the way it runs now. The catch was that it could not stop. Stock was on the racking, the team was on the floor, and a building site is the last thing you want next to either.
So we built around them. New rooms went up in timber stud under the mezzanine, sheathed in OSB and lined in plasterboard, then finished ready for decoration. We kept the work contained, so no dust or debris found its way into their operation, and the business traded through the whole job without a day of downtime.
- The brief
- Adapt a working warehouse to meet the business's new needs
- The catch
- The business had to keep trading throughout, with no dust or debris reaching its operation
- What we built
- New rooms framed in timber stud under the mezzanine, sheathed in OSB and lined in plasterboard, with door openings through to the warehouse
- Finishes
- Walls plastered, and plasterboard taped and jointed ready for decoration
No downtime
The business kept trading for the whole job.
No contamination
Dust and debris kept out of their day-to-day operation.
Built in place
New rooms formed inside the working warehouse.
From frame to finish

FramedTimber stud walls set out between the steel columns 
BoardedSheathed in OSB, with door openings formed 
PlasteredBare walls brought up to a smooth finish 
ReadyTaped and jointed, ready to decorate